Noida Metro Technical Details
Discuss
this article / Provide your feedback
Back to
Noida Metro
Technical Details for the
Noida Section of Phase II of Delhi Metro
Total Length |
7 KM |
Contractor |
JV between Gammon India Limited and
JMC |
Formal Start Date |
2 August 2006 |
Scheduled Completion Date |
June 2009 |
Total Piles |
900 |
First Contract from New Ashok Nagar
to Sector 18 Noida |
Total Stations on this Stretch |
3 |
Station Location |
Sector 15, Sector 16, Sector 18 |
Length |
3.2 km |
Cost |
94 Cr |
Soil Testing |
Status |
Completed |
Date |
Completed between April and June 2006 |
Details |
Bored 70 Wells for conditioning the soil |
Test Piling |
Status |
Completed |
Details |
Every one KM a pile is to be erected
for tesing the load and stress. |