Noida Metro Technical Details
Discuss
this article / Provide your feedback
Back to
Noida Metro
Technical Details for the
Noida Section of Phase II of Delhi Metro
| Total Length |
7 KM |
| Contractor |
JV between Gammon India Limited and
JMC |
| Formal Start Date |
2 August 2006 |
| Scheduled Completion Date |
June 2009 |
| Total Piles |
900 |
| First Contract from New Ashok Nagar
to Sector 18 Noida |
| Total Stations on this Stretch |
3 |
| Station Location |
Sector 15, Sector 16, Sector 18 |
| Length |
3.2 km |
| Cost |
94 Cr |
| Soil Testing |
| Status |
Completed |
| Date |
Completed between April and June 2006 |
| Details |
| Bored 70 Wells for conditioning the soil |
| Test Piling |
| Status |
Completed |
| Details |
| Every one KM a pile is to be erected
for tesing the load and stress. |
Discuss
this article / Provide your feedback
|
|